Transformer for IDGC of Center and Volga Region

The SRW production complex shipped the TDTN 40000/110 transformer for the Protva substation of IDGC of Center and Volga Region.
Reconstruction of the 110/35/10 kV Protva substation operated by Kalugaenergo involves the replacement of T1 and T2 power transformers with 25 MVA and 40 MVA.
Currently, the facility is under contract supervision. In the framework of the contract, another similar transformer will be supplied to the substation in the future.

Write us

Your message has been send succesfully!

logo

Акционерное Общество "Уралэлектротяжмаш"

Yekaterinburg,
Frontovyh brigad, 22
+7 (343) 324-53-00
secretary@uetm.ru